SCIENCE & RESEARCH CENTER 2351 Euclid Avenue 9/17/75 (75-57) Approved location in the area bounded generally by the Basic Science, Main Classroom, and Chester Buildings. 9/17/75 (75-58) Approved demolition of the Special Studies Modulux and Student Center Buildings and the construction of the Science II Building and adjacent site developments integrated with the existing Basic Science and Main Classroom Buildings. 6/9/76 (76-42) Selected Madison-Madison International and Lipaj, Woyer, Tomsik to provide Associate Architect services as a joint enterprise. 10/14/76 (76-69) Approved Science II preliminary plans. 4/20/77 (77-20) Approved working drawings, specifications and plan documents for bidding purposes. 6/22/77 Rejected construction cost bids and discussed alternatives. 1/12/78 (78-6) Approved revised plans and final construction cost estimates for bidding purposes. Several add/alternatives were included in the plans and specifications. 4/19/78 (78-30) Established Science II project budget at $13 million. 4/19/78 (78-30) Approved Science II construction contracts. Rescinded: 5/5/78. 5/5/78 (78-34) Rescinded resolution 78-30, awarding Science II construction contracts, Approved $13,500,000 project budget, and awarded construction contracts: general work Panzica Construction Co. electrical Doan Electric plumbing Smith & Oby hvac Feldman Mechanical fire protection E. B. Katz environmental Western Environmental casework American Desk Manufacturing Co. 9/10/80 (80-42) Approved $90,383 additional compensation to Panciza Construction Co. 1/14/81 (81-5) Officially named "Science & Research Center". 4/17/85 (85-48) Selected Wheeler & Molena as Associate Architect for the Science & Research Center Improvement Project. 9/15/06 (06-61) Authorized soliciting proposals for energy conservation savings measures in the implementation of the fume hood renovation project. 10/8/07 (Board Officers' Resolution 2007-09) Fume Hood Energy Conservation Project contract with Brewer-Garret Co. Approved. (see: BOT Meeting 11/16/07) 3/25/14 (14-09) Delegated authority to the University Administration to enter into a contract with the lowest bidding Science & Research Building roof replacement and penthouse wall modification contractor for a sum not to exceed 10% of construction cost or $2.85 million. 9/29/17 (17-78) Approved contract increase for architectural/engineering services for Engaged Learning Lab renovations 3/23/18 (18-34) Approved contract increase for architectural/engineering services for Engaged Learning Lab renovations 6/29/18 (18-68) University Administration authorized to contract for architectural and engineering services for engaged learning laboratory renovations. 9/20/18 (18-81) Approved contract increase for construction mamager at risk services for Engaged Learning Lab renovations also see: Physical Plant Projects