ART BUILDING PUBLIC SERVICE TIRE CO. PROPERTY 2301 Chester Ave. 3/14/73 (73-7) Approved the purchase of property at 2301 Chester Ave. from the Public Service Tire Co. for $290,000. 11/14/73 (73-63) Madison-Madison-International selected as associate architect for planning and coordination of renovation work for the Wilding Building. 11/13/74 (74-64) Renovation planning budget increased from $310,000 to $850,000 in recognition of the more extensive improvements needed to convert the Wilding Building to use by Art Dept. 4/29/75 (75-31) Authorized the Board's Buildings & Grounds Committee to concur in award of Art Building construction contracts and approval of $950,000 project budget. 4/21/76 (76-30) Authorized expenditure of $80,000 from the Utilities & Renovation contingency funds for movable and fixed equipment for the Art Building renovation project. 11/5/78 (78-66) Selected Whitely & Whitely, Inc., as Associate Architects for the Art Building renovation project. 9/10/80 (80-41) Renovation phase II project budget of $345,000 approved and recommended construction contracts: general work $153,500 Shannon Construction mechanical work $ 80,170 Spohn Corp. plumbing $ 14,349 Shedroff Plumbing electrical $ 35,300 Max Oster Electric 1/9/85 (85-4) Energy Modification Project budget of $111,600 Approved and construction contracts awarded: Phoenix Air Conditioning & Refrigeration, Inc. $82,800 Artisan Electrical Contractors $ 7,564 2/21/91 (91-10) Byers Engineering Co. appointed as Associate Engineer for the Art Building improvements. 6/26/91 (91-53) Authorized President to award contracts for Art Building Improvements. also see: Physical Plant Projects